Polaris executed a design-build 7 MW CHP Power Plant for the University of the West Indies. The project consisted of 5 1.4 MW reciprocating engine generators combined with exhaust driven chillers for campus cooling.
- 7 MW of Power Output
- LNG Fueled
- LPG Backup Fuel
- 24kV grid tied switchgear
- Combined Heat and Power Integration w/ existing Campus utilities
Scope of Work
Startup / Commissioning
Schedule
January 2018 – March 2019
Market
Power
Location
Caribbean